Welcome » Commercial (non-residential) » Metal Buildings » National Hanger-Phase 2, Bennington, VT 2006

National Hanger-Phase 2, Bennington, VT 2006

This design build project is a $1,200,000, 22,000 square foot pre-engineered metal building addition to an existing storage warehouse.

The new addition has a 4 overhead door loading dock area; the balance of the building is used for product storage. The building foundation insulation is R-10, the building walls are R-22, and the roof insulation is made up of fiberglass batts and Low E for a total R value of 33.

The mechanical system incorporates a new oil fired boiler that supplies new ceiling mounted unit heaters with thermostatically controlled roof vents.  The electrical system essentially provides efficient area lighting over the entire warehouse and loading dock. The building has a complete “wet pipe” sprinkler system. Construction began in August 2005 and completed January 2006.


Back to Metal Buildings